West Wylam Sewage Pumping Station

Our experienced contractors: Interserve, plan to carry out this work from 7th January 2019 to 9th October 2019. This essential work will involve the refurbishment of West Wylam Sewage Pumping Station which is situated on Porterhouse Lane and installing a pipeline between West Wylam Sewage Pumping station and Prudhoe Sewage Treatment Works, this will be carried out Monday to Friday between 8am and 5pm. If we have to work outside these hours we will let you know.

Update by Brian Hall

Hello everyone

We have finished the stage of work on the playing fields and have started reinstatement. It looks a bit muddy at the moment but once its seeded and grown back it will look lovely.

We are currently making good progress but previous problems with excavation has held us up and we are a little behind schedule. Hopefully we should be finished at site by early November, we will keep you updated on this.

Thank you for bearing with us during this phase of the works we understand the extra road traffic, noise and disruption has been an inconvenience. The disruption should decrease now as we are finishing off on the playing field area next week and moving on to the stage from the allotments down to Wylam Woods taking our work away from the houses.

I hope you all have a lovely weekend; the weather looks great let’s hope it continues

Brian

 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers