West Wylam Sewage Pumping Station

Our experienced contractors: Interserve, plan to carry out this work from 7th January 2019 to 9th October 2019. This essential work will involve the refurbishment of West Wylam Sewage Pumping Station which is situated on Porterhouse Lane and installing a pipeline between West Wylam Sewage Pumping station and Prudhoe Sewage Treatment Works, this will be carried out Monday to Friday between 8am and 5pm. If we have to work outside these hours we will let you know.

Project updates

Update by Amanda Hunt

Morning Everyone

If you've been following this project you may remember that we have completed the main body of the work around Chrsistmas time and committed to carry out the reinstatement work when the weather improved.   

That work is scheduled to begin from Monday 1 June and we hope to be complete by Friday 3 July, subject to the Covid-19 situation.

Please find below a copy of the letter issued to residents earlier today for more information on the work to be carried out. 

Thanks

Amanda

Our Ref: SN017/0072

29 May 2020

Dear Customer

Important Information about our work in this area

I hope you and those close to you are staying safe and well during these challenging times.

Whilst I’m sorry for the short notice, I wanted to let you know about some very recent and positive developments.

You may remember that I wrote to you during November 2019. I explained the need for us to return in the spring of this year to complete reinstatement as the final part of the work we undertook in West Wylam last year.

I’m sure you will be aware of the current restrictions in force that are affecting the vast majority of businesses in the country, including Northumbrian Water. Throughout the COVID-19 pandemic, all our work has been carried out in line with Government and NHS advice. This remains the position and has certainly placed restrictions on some of our work activities.

In the case of our work in West Wylam this has prevented us completing the final part of our project as quickly as we anticipated however, I’m now pleased to be able to confirm our intention to return to site.

The work will be carried out by our supply partner, Interserve, who will return to site on Monday, 1 June 2020. We anticipate completing the work by Friday, 3 July 2020 however, as I’m sure you will appreciate, due to the current situation affecting the country, we remain open to the possibility that unexpected delays may occur.

During our time on site, we will be based in the main pumping station at the bottom of Hagg Bank. The work itself will consist of; the reinstatement of the ‘Grasscrete’ carpark in the allotments; cultivating, re-seeding and planting of trees in the area between the allotments and the road and reinstatement work within the football field.

Please bear in mind that it may take a little time for the seeding and grass to re-establish.

All of the work outlined above will be undertaken using a small excavator, which is considerably smaller than those used during the main works. You can also expect to see a small ‘dumper’ and road-roller in use.

As a result of the Covid-19 restrictions, our supply partner’s liaison representative will not be available on site. We would therefore request that, if you require any further information or assistance, please don’t hesitate to get in touch with our customer centre via email by logging onto www.nwl.co.uk.

You can also find out more information about our project on our community portal at www.nwlcommunityportal.co.uk and following the link to the ‘West Wylam Sewage Pumping Station’ page. Updates will be posted there and you will find advice and answers to some frequently asked questions.

You can also follow us on twitter @nwatercare and @NorthumbrianH20.

Finally, I would like to take this opportunity to say thank you for your patience and support throughout this work; it’s really appreciated.

 

Yours faithfully

 

Simon Cossar

Project Manager

 

 

 

 

 

 

 

 

Please Login in order to comment on this update.

Update by Brian Hall

Hi everyone

Work is substantially finished at site now with most areas reinstated. We are finishing for the Christmas break today and will return in the new year for a couple of weeks to finish off. Wishing you all the the best for Christmas and the New Year

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

Work is now progressing well with lots of activity along Eastwoods Road next to the allotments which is where the pipeline is up to now. We will be reinstating from the entrance to the allotments back towards the playing fields while pushing on down the hill towards the overbridge. We are hoping to be finished the main part of the work by the end of this month and be clear from site by Christmas with just some reinstatement and tidying up work afterwards. We have adjusted the timeline accordingly

 

Please Login in order to comment on this update.

Update by Brian Hall



*Temporary traffic lights*
Hello everyone, just to let you know we will be putting traffic light controls on Eastwood Road/Haig Bank from
Wednesday 6th November for up to 3 weeks in order to carry out reinstatement work
to the road and dry stone wall 
Our apologies for any inconvenience this may cause. We will try to complete the
work as soon as possible
If you have any questions or concerns please contact me or one of our site team
 

Hope you all have a great weekend

Brian

Please Login in order to comment on this update.

Update by Brian Hall

*Temporary traffic lights*

We will be putting 3 way traffic light controls on the junction with Broomhouse Road and the access road to the recycling centre and  Football Club from the 16th of October for around 3 to 4 weeks to enable us to work under the road to the pumping station. Can I apologize in advance for any inconvenience this may cause, we will try to complete the work as soon as possible, again thank you all for your understanding and patience while these essential works are being carried out

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

We have finished the stage of work on the playing fields and have started reinstatement. It looks a bit muddy at the moment but once its seeded and grown back it will look lovely.

We are currently making good progress but previous problems with excavation has held us up and we are a little behind schedule. Hopefully we should be finished at site by early November, we will keep you updated on this.

Thank you for bearing with us during this phase of the works we understand the extra road traffic, noise and disruption has been an inconvenience. The disruption should decrease now as we are finishing off on the playing field area next week and moving on to the stage from the allotments down to Wylam Woods taking our work away from the houses.

I hope you all have a lovely weekend; the weather looks great let’s hope it continues

Brian

 

Please Login in order to comment on this update.

Update by Brian Hall

Hi everyone

We are going to have to close the road bridge again. There will be no access to the A695 over bridge to Wylam during this period. As before residents will have 24 hour access to properties but wont be able to exit towards the A695. Closure from Monday 19th August 2019 until Monday 6th September 2019. Any problems or concerns please give us a shout

regards

Brian

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

We are removing some of the roadway mats from the field this week in order to allow access for ball netting to be installed for the football fields. We will be replacing the matting afterwards. Work is continueing well now and we have made good progress on the excavation work for the chamber holes.

I hope the road closure is not causing any issues, please let us know if it is. It will be in place until next Friday 5th July if all goes well

Best regards

Brian

 

 

Please Login in order to comment on this update.

Update by Brian Hall

*ROAD CLOSURE*

Hello everyone

In order to facilitate essential work there will be a road closure in place between Monday 24th June 2019 to Friday 5th July 2019

There will be no access to the A695 over bridge to Wylam during this period

During this road closure residents will have guaranteed 24 hour access to their homes

Advance warning signage will be put out by our traffic management company Total Resource w/c 10th June 2019

If you have any questions or concerns please contact me or one of our site team

Many thanks

Brian

 

Please Login in order to comment on this update.

Update by Brian Hall

Hello everyone

Following complaints about the piling activity carried out last week we have met with our contractors Waitings and having stopped piling on this project

Although we are certain the vibration level readings were under permissible levels it was clear this method was creating distress and worry to local residents, particulary in the houses directly opposite the work site. We will proceed with the installation of this pit using a man hole box system rather than piling. This means there will be no more vibration or banging to cause annoyance

Thank you all again for your patience while these essential works are being carried out and sorry if we have caused you any inconvenience

Best regards

Brian

 

 

 

 

 

 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers