Good morning,
This week the team have constructed the new flow meter chamber, including the drainage outlet pipework from the flow meter chamber to wet well. The rising main pipework has been installed and partial reinstatement complete.
The cover slab to wet well chamber has been installed and remedial works within are complete.
Within Northumbrian Water works the air valve and washout chambers are nearing completion including the gravity sewer pipework.
Lets hope we see more sunshine to allow the team to continue with reinstatments.