Good afternoon,
Last week the crew completed their investigation work to the watermain. They reduced ground levels and removed spoil from site, in the area of the proposed new tertiary treatment plant.
This week the crew are currently installing scaffold to the redundant primary tank in preparation for refurbishment works. Following the scaffold install we will be removing the existing scum boards, diffuser drum and associated metal work.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.
Thank you
Rachel