GENERAL PROJECT

Kelloe Upgrade

Starting in Autumn 2022, as part of a £6.4 million scheme, we will be carrying out essential work to improve the performance of our wastewater treatment works in Kelloe. The scheme will help to improve the water quality of the Coxhoe Beck, as well as the watercourses downstream. We are yet to confirm an exact date when the works will commence, however this is likely to be early October 2022 to commence ground stabilisation works, however we will confirm this closer to the date.

Project updates

Update by Rachel Rutter

Good afternoon,

Work within the primary tank has continued this week with the team completing the replacement of the half bridge scraper.

The new desludge pump has been commissioned and the temporary treatment equipment has been decommissioned and is being removed from site this week.

The team are progressing with the preparation and installation of hardstanding areas and footpaths.

Hope you all have a great weekend!

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning all,

Hope everyone is well!

The team have been busy over the last few weeks and have completed the chemical dosing area including a safety check for delivery of chemicals and a water test.

Work commenced to de-commission the existing tanks including isolation of the tanks and backfilling operations.

The team have also been working with sub-contractors and have installed various covers/frames and chambers to the site.

Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning all and a Happy New Year!

You may have seen myself and my colleague Annah in the area this week, having a look at the Kelloe Sewerage Treatment Works and the progress the team are making.  

Since returning back to work after Christmas the crew have completed the duct installation and finished the chemical dosing slab (let’s hope their wrapping up warm in this weather).

The crew continue to progress with work before testing stages take place. Come back next week for further updates.

Thank you for your time. Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning,

Hope everyone is doing well.

Last week the team commenced works to the new chemical dosing area as excavation work is now complete. The installation of ducting is now being carried out.

Our contractor Retroflo have been carrying out commissioning works and are currently in the process of installing the new desludge pumps.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you

Rachel 

 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

This week the team have completed an inspection of the existing primary tank with flows temporarily diverted through the refurbished primary tank.

The final pipe work connections to the new tanks and chambers have been completed along with the desludge chamber pipework and actuated valves.

Installation and commissioning of new pumps to the interstage pump station has been carried out.

With completion of the above works the team are now currently in the process of turning flows through the new humus settlement tank then onto the new tertiary treatment plant.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Have a great weekend!

Rachel 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning,

I hope you are all doing well.

This week the team have been carrying out the installation of wash out drainage line from the new tertiary treatment plant. The crew have installed ducting for the Chemical Dosing point of application.

Electrical installation to the new tertiary treatment plant is ongoing with the removal of scaffold from refurbished primary tank.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you

Rachel 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning,

I hope you’ve had a lovely weekend.

The team have completed the installation of the new desludge chamber and the pipework connections.

Installation of the media and diffusers to the tank have been installed internally and the pipework and blowers have been installed externally.

Along with the above the crew have continued with duct installation and various pipework connections.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you

Rachel 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon

This week the team has completed the mechanical installation to the half bridge scapers and the distribution chamber installation to the humus settlement tank.

The team are currently testing the new tank which has been constructed.

The new power supply has been connected to the site and the cable installation to the new process plant and equipment is being carried out.

Daisy the cow made an appearance this week to see how we are doing!

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Have a great weekend!

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning

Last week and continuing into this week the team continue their work to the new humas settlement tanks which are currently being installed.

Duct installation work is ongoing in different areas of the site and the construction of the NSFA tank has started.

You may see Retroflo in the area while they carry out ancillary work in preparation for the electrical installation to the new plant.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Have a great day!

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon

This week the team have been full steam ahead and installed the new power supply cable.

They have also installed the filter feed pipe and reinforced the concrete base which has been constructed. The access steel to the humus settlement tanks is now in place and the crew continue with the duct installation.

The crew have had no further unexpected visits from Daisy but continue to admire from a far.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Have a lovely weekend!

Rachel

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers