Update by Rachel Rutter
Good morning
Is everyone enjoying the sun!
Last week the team completed coating works and the removal of scaffold from the existing pyramidal primary tank. They are continuing with the installation of reinforcement steel to the new humus tank bases.
Construction of new distribution chamber base slab is complete along with the excavation works for the base slab and installation of earth rods for the new MCC. Excavation works for the bases to the new tertiary treatment plant are underway.
This week the team continue with the installation of reinforcement steel to the new humus tank bases.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.
Have a lovely day!
Rachel