Starting in Autumn 2022, as part of a £6.4 million scheme, we will be carrying out essential work to improve the performance of our wastewater treatment works in Kelloe. The scheme will help to improve the water quality of the Coxhoe Beck, as well as the watercourses downstream. We are yet to confirm an exact date when the works will commence, however this is likely to be early October 2022 to commence ground stabilisation works, however we will confirm this closer to the date.

Update by Rachel Rutter

Good afternoon,

This week the team have completed an inspection of the existing primary tank with flows temporarily diverted through the refurbished primary tank.

The final pipe work connections to the new tanks and chambers have been completed along with the desludge chamber pipework and actuated valves.

Installation and commissioning of new pumps to the interstage pump station has been carried out.

With completion of the above works the team are now currently in the process of turning flows through the new humus settlement tank then onto the new tertiary treatment plant.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Have a great weekend!

Rachel 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers