Update by Rachel Rutter
Good afternoon,
Work within the primary tank has continued this week with the team completing the replacement of the half bridge scraper.
The new desludge pump has been commissioned and the temporary treatment equipment has been decommissioned and is being removed from site this week.
The team are progressing with the preparation and installation of hardstanding areas and footpaths.
Hope you all have a great weekend!
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Rachel