Update by Rachel Rutter
Good afternoon,
The team have started with the commissioning of the new chemical dosing system which will start to add chemicals into the treatment process. They are currently working to optimise this to achieve the best possible results.
Works to install the new hardstanding’s are ongoing around the pieces of plant installed earlier in the project and the team are currently working to install a new concrete road replacing the existing through the treatment works.
Hope you all have a great week!