The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT

Kelloe Upgrade

Starting in Autumn 2022, as part of a £6.4 million scheme, we will be carrying out essential work to improve the performance of our wastewater treatment works in Kelloe. The scheme will help to improve the water quality of the Coxhoe Beck, as well as the watercourses downstream. We are yet to confirm an exact date when the works will commence, however this is likely to be early October 2022 to commence ground stabilisation works, however we will confirm this closer to the date.

Update by Rachel Rutter

Good morning,

Over the next couple of weeks, the team will continue with optimisation of chemical dosing to the treatment process, on site lab analysis is being carried out daily to monitor the quality of the effluent during the chemical dosing optimisation period.

The team are continuing with reinstatement of site access roads alongside general tidying, reinstatement and landscaping works.

Thank you for your time!

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers