&cropxunits=602.9923706054688&cropyunits=1071.998046875&width=40&height=40&mode=crop)
Update by Jane Cooper
Hello,
All the temporary pipe work has been set up supplying flows to the temporary High Sensitivity Acoustic Flow Sensors.
In the next month or so we will be demolishing the existing tanks and removing them from site. These tanks will be transported from the site using the farmer's access track meaning little or no impact to the walkers and dog walkers who use the access track to the site.
We will deliver and install new critical infrastructure at the end of February 2025, and complete all above ground pipe work and power up the new plant in March 2025
All being well the works should be substantially complete by mid May 2025.
Please Login in order to comment on this update.