Good Afternoon,
After visiting site this morning I thought I'd let you know the progress......
We are progressing well and to programme and whilst Gary is away on his honeymoon, Steve Masters will be looking after the site.
Steve has plenty of experience and he has been currently working at another one of our sites in Northumberland, this time at Murton Water Treatment Works, check out his photo.
Installing the primary settlement tanks have gone well, they have been filled with water and have been passed which means the sheet piling holding them can be removed next week, that happening is a milestone for this job.
Please don't forget please get in touch if you want to ask me any questions about the project.