The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT
CURRENT WEATHER
7°C

Wooler Wastewater Treatment Works

Install chemical dosing to improve treatment of flows and, in particular, to control the level of phosphorus discharges to Wooler Water, to the satisfaction of the Environment Agency. Construct two new radial Primary Settlement Tanks and ancillary equipment to improve separation of solids for removal by road tanker. Improvements to screening at inlet chambers, plus mid-pipeline pumping station and emergency generator to safeguard the Works in the event of a local power failure. Refurbishment of welfare building.

Project updates

Update by Joan Tatters

Good Afternoon,

As you know, work started in April 2019 on the project to improve the resilience and performance of the existing Sewage Treatment Works on the east bank of Wooler Water off Weetwood Road. The work undertaken has comprised the provision of additional process units to serve the increasing population and provide an enhancement of the treatment process to improve environmental protection for the years to come.

We are pleased to advise that all the construction work is now complete. You may have noticed the access track into the works has been resurfaced and the gates and boundary fencing realigned to improved safety. With the current Covid-19 situation we are unable to remove skips and welfare cabins, as soon as the situation improves and suppliers return to work these items will be removed from site, I will let you know in due course.

Thank you for your co-operation and patience during our work we really do appreciate it, and should you want to discuss this further or just ask a question about the project please feel free.

Everyone on this project would like to take this opportunity to say "thank you" for your patience and support throughout this work.

 

Please Login in order to comment on this update.

Update by Joan Tatters

Good Morning

It's been a while since my last blogg, so I thought I would just forward you some photos of how things are progressing on site.

Although the weather hasn't been the best it hasn't hindered Gary and the team, they are now back on track and even the Christmas shut down didn't affect them.

Please Login in order to comment on this update.

Update by Joan Tatters

Hello,

Yesterday I was out and about in the village dropping in letters explaining  the deliveries we are expecting next week.

Week commencing 7th October we will be taking delivery of two large pre-fabricated cabins which house the dosing equipment essential to controlling the level of discharges to the river. Since these contain important (and sometimes delicate) devices, they need to be in a weatherproof structure.

On Monday 7th we will be preparing the site to accept delivery of the cabins and as they are of considerable size the vehicles delivering them will require enhanced space. This means we will need to reconfigure the existing fence and gate arrangement to both the vehicular and pedestrian entrances (which are actively used by walkers) and slightly prune back any overhanging branches.

Tuesday 8th, they are planned to arrive morning and lunchtime respectively and with that in mind we graciously request customers not to park any vehicles at the entrance of the site for safety reasons during this time. Later that day the team will reinstate the fence and gates to the public walkway, ensuring all is back to normal as quickly as possible.

Your health and safety are paramount to us and if you are out and about during this time please be that little more vigilant.

Thank you for your co-operation and patience during our work we really do appreciate it.

Please Login in order to comment on this update.

Update by Joan Tatters

Good Afternoon,

After visiting site this morning I thought I'd let you know the progress......

We are progressing well and to programme and whilst Gary is away on his honeymoon, Steve Masters will be looking after the site.

Steve has plenty of experience and he has been currently working at another one of our sites in Northumberland, this time at Murton Water Treatment Works, check out his photo.

Installing the primary settlement tanks have gone well, they have been filled with water and have been passed which means the sheet piling holding them can be removed next week, that happening is a milestone for this job.

Please don't forget please get in touch if you want to ask me any questions about the project.

 

Please Login in order to comment on this update.

Update by Roger Smith

Good Afternoon,

Just following on from Joan's post, I thought I'd add a little more............

Progress has continued on site, and thankfully with few setbacks due to occasional downpours. Our main focus has been the construction of the two Primary Settlement Tanks , which are a combination of large pre-cast concrete components (you may have noticed some being transported to site) with poured concrete and reinforcement bars ‘stitching ‘ the sections together.  So- few setbacks ?  Yes, even though the excavations for these Tanks are much lower than ground level, occasional pumping has been effective in controlling groundwater levels, hence no unplanned interruptions.

Aside of the above, some new below-ground pipelines have been installed, and a new generator plinth to ensure the continuous running of pumps in the event of a local power cut. In the next few weeks we will commence the large concrete plinths to house the Chemical Dosing Kiosks , which are fundamental to managing the amount of discharge to the Wooler Water.

Lastly, many of you will have noticed the major earthworks adjacent to the road to Chatton. This is part of the proposed housing development , in which Northumbrian Water are not involved, aside of arranging the usual connections.

Please Login in order to comment on this update.

Update by Joan Tatters

Good Afternoon,

No words.................actions speak louder

Please Login in order to comment on this update.

Update by Joan Tatters

Good Morning All,

Here is your update

This is the hopper unit within the primary settlement tanks which has now all pipework installed.

The concrete blinding is being placed for the pre-cast wall units that arrived last Monday. There will be the need to use a large crane so please be that little more vigilant if you are travelling through Wooler. 

Here is a little montage of photos for you.

 

Please Login in order to comment on this update.

Update by Gabrielle Ward

Good Morning All,

Just a quick update for you!

Construction work is progressing well , helped by the generally good weather that we have experienced during the initial earthworks. The metal sheet piles holding-up the deep excavations for the two new biological filters thankfully went into soft river basin soils (no boulders !) so these could be pushed in using vibratory techniques, avoiding the noisier 'hammer' technique more common in harder ground. We are currently transporting crushed rock to form a layer in the bottom of these 2 large holes (before concrete is poured on top) ..hence there will be more frequent lorry movements through the main gate on the B6348 Chatton Road. Current thinking suggests that this period will actually be the busiest in terms of lorry movements.  But some heavier one-off components are due for delivery soon , so please approach the Metal Bridge slowly (especially when heading towards Town Centre) in case a wide load is approaching the narrow section of the bridge.  In summary - all going well to date - and we remain on schedule !!

 

Please Login in order to comment on this update.

Update by Joan Tatters

Good Morning,

Hope you had a great Bank Holiday.

Just a quick update...........

Gary and the team are making great headway..........they have started to excavate and pile for the 1st primary settlement tank. It's a lengthy process that will  take approximately 2 weeks to fully excavate and base out.

Here are a couple of shots of the machine lowering frames which will brace the sheet piles.

 

Please Login in order to comment on this update.

Update by Joan Tatters

Good Morning,

Well, what a difference 4 weeks make!!!!

Gary and the team have been soldiering on setting up the compound and generally gettting things in place to start the work. Here are some photos from site. I will be up there next week and will drop in and see a few of you just to see how things have been going.

Don't forget if you want to ask me any questions please feel free or if you see any of the team they will always be happy to help.

Joan

 

 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers