Update by Stephen Bennison
Hi all
Just a quick update on our progress over the last week, we have continued to install the new sewer but unfortunately this has been slower than we would have liked due to difficult ground conditions.
We have encountered a lot of sand and water which when mixed together makes our job hard but we now have a plan in place to overcome these difficulties and hope to make some good progress. As a result of this we plan to continue with our saturday working to regain lost time.
Hope you are all looking forward to having a lovely weekend, although the weather forecast isnt great.
Steve