GENERAL PROJECT

Belford Street, Peterlee

At Northumbrian Water looking after the environment and reducing the risk of flooding are two of our top priorities. As part of this commitment we want to make you aware of some sewerage network investigations in your area. We intend to carry out a study of the area to identify a potential solution to help protect the environment and ensure that our sewer network continues to serve the community effectively.

Project updates

Update by Rachel Rutter

Good Afternoon All, 

I am pleased to tell you the work has now been completed, which includes post & wire fencing, and also the Palisade fencing to Hepworths compound.

The site team have fixed the existing fencing and have straightened the posts to the East Fence. 

We have now left site. 

If you have any queries at all regarding our work in your area, please do not hesitate to contact us.

Thank you

Rachel
 

Please Login in order to comment on this update.

Update by Rachel Rutter

Hi All,

The site team has now made sure all Surface Water and Foul Sewer pipe work installation has been completed. 

Reinstatement works are currently being carried out, which means that the project is nearing completion.

If you have any queries at all regarding our work in your area, please do not hesitate to contact us.

Thank you

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Morning All,

Hope you had a lovely bank holiday weekend, i'm sorry for the delayed update.

As you may have noticed to the West side of Kilburn Drive landscapers have placed grass and wild flower side to the mound.

The fences arrived on site on 31 May and due to the quick work of the site team, post and wire fencing is now complete across the site. 

This week the site team are starting the palisade fencing around the former compound site and the removal of heras fencing from both sides of Kilburn Drive and Belford Street.

Should you have any questions please email me on NWL.Customer@esh.uk.com.

Thank you 

Rachel 

Please Login in order to comment on this update.

Update by Becky Gartland

Hi All, Hope you have had a lovely bank holiday weekend. 

We have carried out the following: block paving and kerb reinstatements, we have reinstated the compound in which our welfare was set up and de-mobilised the site by offloading all excess/waste material, off hired all plant/equipment/tools/cabins. 

We still need to complete the following:

Reinstate palisade fence in existing yard

Wildflower seeding to the embankment just off Belford Street

Install post & wire fencing site wide

And grass seeding to both sides of Kilburn drive

 

Work due to start Thursday 5 May 2022.

Any questions please contact me.

 

Regards 

Becky 

 

Please Login in order to comment on this update.

Update by Becky Gartland

Good afternoon all, 

I hope you all had a lovely Easter Bank Holiday Weekend!

Just a quick update for you on how things have been going with the reinstatements in the area. 

Last week we carried out the tarmac reinstatements at the bottom of Belford Street along with surfacing works and footpath repairs on Kilburn Drive.

Over the course of this week the site team will be reinstating the site compound area to the rear of businesses off Kilburn Drive. 

Following this we will be arranging to reinstate the pallisade fencing along with wildflower and grass seeding on the woodland areas surrounding Kilburn Drive and Belford Street. I will keep you all updated on when this is expected to take place. 

If you have any queries at all, please do not hesitate to contact me. 

Thank you 

Becky 

 

Please Login in order to comment on this update.

Update by Becky Gartland

Good afternoon, 

Just a quick update on how our reinstatements are going on site. 

The site team have laid the topsoil between Belford Street and Kilburn Drive along with an area that has been block paved to the west of Kilburn Drive. 

Further ground works will be carried out to the rear of business units on Kilburn Drive over the rest of this week. 

Wildflower seeding is planned to take place week commencing 4th April in the embankment area adjacent to Belford Street. 

This will be followed by final tarmac reinstatements week commencing 11th April. 

As always, if you have any queries regarding our work, please get in touch with us. 

Regards 

Becky 

Please Login in order to comment on this update.

Update by Becky Gartland

Good afternoon,

It's been a few weeks since I last provided you all with an update so wanted to let you know what's been happening on site. 

The team have been carrying out topsoiling operations between manholes within the embankent and surrounding working areas. 

Landscaping works will continue across site over the coming weeks. 

If you have any queries at all, please let me know. 

Thank you 

Becky 

 

Please Login in order to comment on this update.

Update by Becky Gartland

Happy Friday everyone!

Just a quick update regarding our progress on site. 

Things have been progressing well, the work at the bottom of Belford Street was complete last week and the road closure removed. This area will need to be revisited for a short period of time in order to complete resurfacing works, but I will keep you all informed of when this will take place. 

We have also cleared the concrete mass within the embankment area and the pipework has now been installed within the trench. 

Next week we will be completing final connections with the compound area followed by reinstatements across the remainder of our working areas. 

Have a lovely weekend!

Thank you 

Becky 

Please Login in order to comment on this update.

Update by Becky Gartland

Good morning all, 

Hope you had a lovely weekend despite the stormy weather!

Work is going well within the road closure at the end of Belford Street and we forsee this area to be completed by the end of this week. 

Here's a few images off Steve showing how the site team progressed last week. 

Thank you 

Becky 

Please Login in order to comment on this update.

Update by Becky Gartland

Good morning all, 

Just a brief update for you this week as the site team have been working to get through the mass of concrete within our current working area in the grassed embankment between Kilburn Drive and Belford Street. 

They are however going to be progressing onto the closure at the bottom of Belford Street from Monday 14th February 2022 which is expected to be in place for up to 2 weeks.

Any questions at all, please get in touch. 

Hope you all have a lovely weekend!

Becky  

 

 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers