Update by Jane Cooper
Hello,
Please find latest updates, together with photos, from our Fishburn Site.
The construction phase of this project is now complete.
There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.
At Northumbrian Water, looking after the environment is one of our top priorities. As part of this commitment, we are working with our supply partner, Galliford Try Construction to undertake upgrade work at Fishburn sewage treatment works (STW) to improve the performance of our wastewater treatment. This essential work will help to improve water quality and ensure that the treatment facility continues to serve the community effectively.
Hello,
Please find latest updates, together with photos, from our Fishburn Site.
Hello,
Please find latest update together with photos, on the Fishburn project.
https://northumbrianwater.blob.core.windows.net/projects/287/FishburnOct2024.pdf
Please Login in order to comment on this update.
Hello.
We are happy to say that construction works are now fully complete, and we are now in the commissioning phase.
See some more specifics and associated photos in the attached.
Please Login in order to comment on this update.
Hello,
Since the last update, works have kept going even though we have had the wettest Winter for 35 years!
The scheme is still on track to be completed as per the original program, to end in/around August 2024.
See the attachment showing photos of the works:
Please Login in order to comment on this update.
Hello
I’d like to introduce the team from Galliford Try that will be completing the work at Fishburn on behalf of Northumbria Water. My name is Jane Cooper, and I am the Customer Experience Coordinator for Galliford Try. Our Site Manager is Stephen Rudkin and our Project Manager is John Goose.
Since commencing on site early December, the team have worked through some horrendous weather conditions but have tried to maintain progress. The team completed the site set up ahead of the Christmas shutdown to ensure a good start in the new year. During this month (January), the team have been carrying out the bulk excavations and stoning operations to the proposed chemical dosing/tertiary treatment and roads ways.
The team have also been excavating and building the proposed new Pumping station.
See the attachment showing photos of the works.Construction Photos
I’ll keep you updated with progress on this project portal, but if you have any questions, you can either quickly create an account to comment on any activity updates on this page, or alternatively, use the ‘Contact’ button at the top of the page, whichever way is best for you.
Please Login in order to comment on this update.
Work started on the 4th December on the upgrade work to the treatment works.
With agreement from Durham CC, we’ve established a temporary site set up just outside the works and created an additional area for parking. Please note that access to adjacent footpaths will be maintained throughout the construction phase, however, caution should be taken when crossing the access track.
We’ll be shutting down for the Christmas period on Wednesday 20th December and will return on Tuesday 2nd January when we’ll start to progress the upgrade works within the site.
Best wishes over the Christmas and New Year
Please Login in order to comment on this update.
Good morning and apologies, we've not updated the portal for a quite a while now.
We wrote to customers back in September to confirm that we have now secured business approval for the upgrade works and are progressing with the detailed design. We plan to start construction work in December 2023 and expect the upgrade works to take up to 8 months to complete. Now that we are preparing to move into the construction phase, we'll make sure to kee pthe portal updated regularly so you can see how we are getting on.
Again, don't hesitate to contact us either via the 'Contact Us' tab above or comment on this post and we'll get back to you.
Thanks
Please Login in order to comment on this update.
Good afternoon,
I hope you had a lovely Christmas and settling into the New Year.
We’d planned to start some preliminary ground investigation works starting tomorrow, but unfortunately, we are delayed, and they will start on the 24th January.
If you have any questions, please don't hesitate to contact us by commenting below or calling Northumbrian Water on 0345 7171100.
Many thanks
Kat
Please Login in order to comment on this update.
At Northumbrian Water, we work to make a difference in your community.
Have you considered a career that can help you do the same?
As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.
You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.
Please Login in order to comment on this update.