Update by Bethany Oakley
Important information about work in your area
We recently wrote to you about our work to install a new sewer pipe along Bow Street and Gresham Road and the requirement for completing these works in three phases, to try and minimise disruption as much as possible.
We mentioned previously that due to the nature of our work, and for the safety of our Customers and our Site Team, a rolling closure is required as we progress through each phase of the works.
We are nearing completion of phase 1 and therefore, phase 2 of our works will commence on Monday 24th March and will take six weeks to complete, this includes out investigation works, before moving to Phase 3.
We will try to maintain emergency access during our working hours, ensuring emergency vehicles can get as close to the properties as possible.
You can find the plan of each phase, and the road closure for phase 2 on page 3 on this update.
We apologise for any inconvenience this may cause however, should you require any assistance, our site team will be happy to help you.