Update by Rachel Rutter
Good afternoon,
The team have now got the Mecana filter base in place and ready to accept the Mecana filter tank which will be delivered Tuesday 2 April 2024.
Connection works taking place outside of the working area will be completed this week and security palisade fence-line reinstated.
The pumping station wet well is now installed and benching in the base has been completed and ready for mechanical electrical & pumps to be installed.
Inter-connecting pipework around site continues ahead of programme.
Thank you for your time. Have a great weekend!
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Rachel