GENERAL PROJECT

Hustledown Sewage Treatment Works Upgrade

We are investing £4m to improve the performance of our sewage treatment works at Hustledown. The work will involve the installation of new equipment which will provide additional chemical removal before the final effluent is discharged. This will aid NWL in improving the quality of rivers and coastal waters for the benefit of people, the environment and wildlife.

Project updates

Update by Alice Blackett

Good Afternoon All

I hope you are well.

We have now successfully connected the rising main to the Pumping Station pipework. The Pumping Station pipeworks are currently 80% completed.

Roadworks and footpaths within the Treatment Works are currently 90% completed.

The Mecena Units now have water in to the requested levels ready for commissioning.

I hope you all have a good weekend.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Please Login in order to comment on this update.

Update by Alice Blackett

Good Afternoon all and happy Friday!

Construction of the new road is now well underway from the new Flow Meter Chamber to the Mecana Filter units.

The pipework to the Pumping Station is currently being installed and all cable pulling is now complete. These works will allow us to change flows to the new system at the end of September, all being well.

The concrete footpath to the outside of the new MCC Kiosk has also been completed today.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Please Login in order to comment on this update.

Update by Alice Blackett

Good Afternoon

Since the last update, the Rising Main has now been successfully tested by an independent testing company and all ducts and draw pits are now constructed.

The above allows cable pulling to commence which is the connection of the existing works to the newly constructed works. This will allow the new works to be powered up and be controlled remotely.

The new pumping station pumps and overground DI pipework/valve chamber works are to commence this week.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Have a lovely week!

Alice

Please Login in order to comment on this update.

Update by Alice Blackett

Good Morning all

A nail-biting weekend is ahead of us whilst England play Spain in the Euro finnals. COME ON ENGLAND!!!

We have also hit a milestone here at Hustledown Sewage Treatment Works as the rising main works are now completed and testing will take place next week.

The works to the Duct Pit and Draw Pit are now 80% complete.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Have a fantasic weekend!

Alice 

Please Login in order to comment on this update.

Update by Alice Blackett

Good Morning

Following our last update, the Kiosk is now watertight around the control pannel and the electricians can commence powering up.

The live tap has now been installed into the existing structure and is working well and both gravity pipelines have now been completed and tested.

Works on the rising main have now been restarted and should hopefully be complete by the weekend.

Please see attached photographs of what our hard working team have been up to.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Alice

Please Login in order to comment on this update.

Update by Alice Blackett

Good morning everyone and happy Friday!

Works are progressing well with the Flow Meter Chamber and By-pass Pipework now complete.

The motor control centres are now in place and the Kiosk has been placed over the top ready for connection to the electric supply. This will be the controls for the new works. 

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

I hope everyone has a lovely weekend!

Alice

 

Please Login in order to comment on this update.

Update by Alice Blackett

Good Afternoon

I hope everyone is well and looking forward to the weekend.

Works are still progressing nicely with the bypass and flow meter. Installation of the Kiosk is also in progress as the ducts have been laid and the concrete base has been poured.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Have a lovely weekend!

Alice 

Please Login in order to comment on this update.

Update by Alice Blackett

Good Afternoon,

I hope you are all well.

Duct and draw pit box works are currently in progress along with the concrete slab works surrounding the pumping station valve. The team are continuing with by-pass pipework and flow meter chamber works.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Thank you for your time.

Alice

Please Login in order to comment on this update.

Update by Alice Blackett

Good Afternoon,

I would firstly like to introduce myself having recently started with Esh, I will now be your point of contact should you have any queries in relation to the ongoing works at Hustledown and I will continue to provide you with updates on a regular basis.

Following on from last week, the portal wall works are now complete and the shaft collar has also been completed to finished levels. The team continue to work on the Flow Meter Chamber and by-pass. The weather couldn’t have been better for the team this week!

Thank you for your time, enjoy your weekend in the sunshine.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Alice

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

Following on from last week the team continue with the pipeline from the shaft to the Mecana filter units. The portal wall extension works to the final effluent chamber has commenced, with the flow meter chamber and by-pass arrangement works continuing.

Lets hope the team have better weather and we see more sunshine.

Thank you for your time, have a lovely week!

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Rachel

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers