Update by Geoff Joyce
Hi everyone
Please find this week's update below:
Marden Road South
Shaft-sinking operations continued throughout the week. Progress has been slower than hoped due to the discovery of an uncharted underground pipe (which proved to be abandoned) and to ground conditions which were more challenging than expected. 4 shaft rings have been constructed and grouting operations continue to make the shaft watertight.
North View/Burnside Road
Pipelaying activities continued in North View just east of the Metro bridge.
Water main diversions have been tested and final connections were made on Friday. These works will continue next week.
Have a nice weekend.
Geoff