The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

RAINWISE SCHEME
CURRENT WEATHER
3°C

Monks Wood, North Shields Surface Attenuation

We are currently on site adjacent to Beach Road. Our scheme is to separate surface water flows from the combined sewerage system and store the excessive flows during storms. To do this, we are constructing new surface water and combined sewers together with a series of cascading basins in which to hold back the flows until the storm subsides and the existing sewerage system can accept the storm water.

Update by Simon Bright

Hi

The weather this week hasn't helped at all, excavations have been flooded out, the route from the compound has been inaccessible and the men have been working in slop!

We've still managed to proceed slowly, having completed 2 manholes next to Ludlaw Avenue and poured the base to the manhole along side the existing pipe next to Whitehouse Primary School. 

It has been a constant battle to keep mud off crossing points and the road, however, road brushes are booked daily and we are brushing up as required. Hopefully this is the end of the prolonged rain for the rest of the summer.

Simon

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers