RAINWISE SCHEME
CURRENT WEATHER
15°C

Monks Wood, North Shields Surface Attenuation

We are currently on site adjacent to Beach Road. Our scheme is to separate surface water flows from the combined sewerage system and store the excessive flows during storms. To do this, we are constructing new surface water and combined sewers together with a series of cascading basins in which to hold back the flows until the storm subsides and the existing sewerage system can accept the storm water.

Project updates

Update by Christine Taylor

Good afternoon,

Following our update yesterday, we would also like to inform customers that we will have a Footpath Closure and diversion in place on Beach Road.  This is to allow our final stage of work to be carried out safely.  The closure will be in place from Monday 20 July to Friday 24 July 2020, from 9.00-15.30, during these times please follow the diversion in place.

We have posted the traffic management plan, which show our diversion on our planned work section.

Have a great weekend.

Christine

Please Login in order to comment on this update.

Update by Christine Taylor

Good afternoon,

Adam, our Senior Engineer on site has sent through a progress update.

Our landscapers have been working this week; harrowing and stone picking from the school down to basin 7, the east end of site. The seeding is to commence either Thursday or Friday.  The fencing has been stripped from whitecliff path back to site entrance, by the back of morrisons carpark.

Our team have started to reinstate the path and pin kerbs to whitecliff path and will start to reinstate the Beach Road site entrance.  All of this works should be completed next Thursday.  The landscaping works shoud be completed by next Friday, except tree planting, which will be autumn time.

We will be demobing the compound at the Leisure centre next Friday 24th July 2020.

I hope everyone has a nice weekend and we will provide a further update next week.

Christine

Please Login in order to comment on this update.

Update by Christine Taylor

Good afternoon,

As you can see we are working on the basins.  Could we ask that whilst the reinstatement and seeding is being carried out, residents refrain from walking across the area.  This will allow the seeds to take and the area to establish quicker.

Thank you in advance.

Christine

Please Login in order to comment on this update.

Update by Christine Taylor

Good morning,

I hope everyone is keeping well?

The site team have sent me an update which I want to share with you.

As you will have seen we have arrived back on site to complete our works, now the weather and ground has improved.  The team have set up the compound in Tynemouth Swimming Pool carpark.  We have had a team carrying out testing of the existing drainage, and an inspection from Northumbrian Water is pending.

On Monday, Northeast Groundworks (GWS) arrived on site. They started with reprofiling the field from Ludlow path to Basin 1. The crew are working down the field, and will be tiding basins as they go.  

This Monday our contract partner Straughans arrive on site, to strim the path to the rear of heras fence, this will assist with customer access to the rear of their properties.  Following this they will spray off self seeded weeds across site.  Straughans will then return in a couple of weeks to commence seeding, cultivating etc.

Have a lovely weekend and I hope the sun makes an appearance.

Christine

 

Please Login in order to comment on this update.

Update by Christine Taylor

Good afternoon,

I have spoken to some residents recently regarding our return to site.  Also you may have seen from our comments on a previous post or from the letter you will have received from Northumbrian Water this week, we are returning to site on the 22 June 2020

We expect to be on site for approximately 6 weeks. 

During this time our works will include:

  • Finishing ground levels for the basins
  • The area will be stone picked and debris will be removed
  • A tidy up of the existing shrubbery will be carried out
  • The grass seed and wild flower seeding will be sown
  • Some tree and shrub planting witll be carried out on both sides of Beach road
  • The wildlife Garden in Whitehouse Primary School will be tidied up and handed over to the school

We want to take this opportunity to reasure you that we will be working strictly in line with the government guidelines around coronavirus and that the safety of our customers and workforce is paramount.

If you wish to discuss this work further or have any concerns please feel free to cotact us via this portal or by calling 03457 171100, and a callback will be organised.

We will see you all soon.

Christine

 

Please Login in order to comment on this update.

Update by Christine Taylor

Good morning,

We wanted to take this opportunity to wish all our customers a Merry Christmas and all the very best for 2020.  We would also like to thank you all for your patience and understanding whilst we have carried out our works, thank you for being amazing!

As you can see by the picture my team are in the festive mood.  Both Tony and Becky are taking time off to be with their loved ones over Christmas along with the site teams, but wanted to show off their Christmas jumpers.

I will be working over the Christmas and New Year period if you have any concerns.  You can contact me by commenting on this post or alternatively calling 03457 171100.

Merry Christmas, stay safe and be kind.

Christine

Please Login in order to comment on this update.

Update by Anthony Birkett

Hi Everyone

I was on site yesterday and had a walk around with Adam to see how we've progressed this week. Over the last few days and into the next few, we're making good progress. We've reinstated the kerbs on Beach Road by our cabins and further up by the school. We've also nominated a contractor to complete the tarmac reinstatements at these locations and also on the Monks Wood side. In addition to this, we're continuing to shape the basins and will be removing the stone used to form the compound from site later this week. We have our landscaping contractor booked to attend site soon to plant trees etc. Things are moving along nicely in the run down to Christmas

I've attached a few photos illustrating the areas I've mentioned

Tony

Please Login in order to comment on this update.

Update by Anthony Birkett

Hi Everyone

I was on site this week meeting with Ashley, Mark and Lawrence to discuss, among other things, the reinstatement plans.

Firstly, around the existing compound area: In the next week, the green cabin will be removed from site - the yellow cabin will remain in place until we pull off for Christmas. We will also be raising the kerb that we lowered to allow access and reinstating the footpath. We are currently working on the basins in this area, having completed the Wear Wall (the timber structure that you may see poking out of the ground). Once we form the basic basin construction we will leave site, although this basin along with the rest will require grading and contouring when we return in spring 2020, we simply can't complete the final grading with current ongoing weather conditions. 

When we leave site we will pull the fencing in as much as we can and trim the bushes and weeds back to allow access around the outside of the fencing area, to the rear of Heybrook Avenue. As previously mentioned, the temporary fencing to the perimeter of the basins will need to remain in place until we return to complete the work in Spring 2020.

We have removed some of the fencing, however the posts that haven't been removed will need to remain in place for now. The ground conditions have made it impossible to remove them right now, so they will be taken out in the Spring.

A little further up Beach Road towards Whitehouse Primary School there is a large gap in the treeline. This gap was present before we arrived, but we will fill it with a shrub mix. Currently we are finding things difficult due to the ongoing poor weather conditions, so if this isn't completed, it will when we return in Spring 2020. (picture 1)

Moving further along again, we have installed a temporary fence alongside the footpath between Beach Road and Ludlow Avenue - this is purely to demarkate the area under reinstatement, as at the moment it is not in a condition that we would be happy to call finished - further landscaping will be required here in Spring as well, which will include regrading, stone picking, cultivating and seeding. (picture 2)

On the other side of this footpath we have installed a fence and a tree line near to Beach Road. There will be another row of trees planted behind this current row to increase the density. This will be done before we leave the area for Christmas. (picture 3)

Alongside Whitehouse Primary School, we will need to reinstate the footpath which runs past the school to Beach Road. We will also remove the Herras fencing on the opposite side of the School and replace this with a temporary post and wire fence that will be in place until Spring 2020. You may have noticed that we are currently working on raising the kerb that we lowered for access and reinstating the footpath, his will be completed soon.

On the other side of Beach Road(the Monks Wood side), there is still work to be done. We are not finished yet. In the next week we will be removing the temporary tarmac ramp installed against the existing kerbline in Monks Wood. Also the existing footpath that we crossed when working in this area has dipped a little, so this will be relayed before we leave for the Christmas break. We also have futher semi-mature tree's to plant in this area, which we are awaiting delivery. The hedgrow removed from the fencline running parallel with Beach Road will also be replanted. (pictures 4 & 5)

When we return in spring all the temporary fencing and associated timber posts will be removed, the basins will be regraded, stone picked, cultivated, and seeded. Temporay post and wire fencing to the verge on Beach Road and the temporary timber fencing to the footpath leading to Ludlow Avenue will remain until the landscaping has established. The temporary site access at the East end of Beach Road will also be reinstated and the footpath crossing point resurfaced. Once completed we have a further twelve months for mainatance, so you will see our landscapig contractor visiting to undertake grass cutting, weed control and general maintance to the perimeter of the site. 

I hope this update provides clarity on our current timescales,

Regards

Tony

Please Login in order to comment on this update.

Update by Anthony Birkett

Hi Everyone

Work has gone well on site this week.

We've planted the trees alongside the fence which was put up last week near to Whitehouse Primary School - these will need to be given time to establish once the weather improves.

We've also continued with preparations for digging the final basin at the other end of site - the stone base is in the process of being removed so we can complete this before leaving site before Christmas.

We will continue to work hard to get the job done as quickly as we can.

Have a nice weekend

Tony

Please Login in order to comment on this update.

Update by Anthony Birkett

Hi Everyone

I've been to site today for a catch up with the team and a walk around to see how we're progressing.

The last week or so has seen a number of visible improvements: we've erected a fence off Beach Road, down towards the school - we've also received delivery of some of the trees and shrubs that will be planted in that area (I've attached a couple of photos of the fence and some of the trees); we've also been working on the landscaping within the school - sadly due to the weather, we had to cancel a planned event there this week (I've attached a couple of photos showing some of the landscaping here as well). There is still a little to do here.

In the next week or two you will notice us starting to remove some of the fencing in preparation for withdrawing. Some of the fencing will remain in place, but we will pull this in as much as we can to allow some access around the outskirts of it - we also intend to cut back some of the overgrowth where necessary.

Regards

Tony

Letter 25 October 2019

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers