Update by Christine Taylor
Good afternoon,
Adam, our Senior Engineer on site has sent through a progress update.
Our landscapers have been working this week; harrowing and stone picking from the school down to basin 7, the east end of site. The seeding is to commence either Thursday or Friday. The fencing has been stripped from whitecliff path back to site entrance, by the back of morrisons carpark.
Our team have started to reinstate the path and pin kerbs to whitecliff path and will start to reinstate the Beach Road site entrance. All of this works should be completed next Thursday. The landscaping works shoud be completed by next Friday, except tree planting, which will be autumn time.
We will be demobing the compound at the Leisure centre next Friday 24th July 2020.
I hope everyone has a nice weekend and we will provide a further update next week.
Christine