Murton (Berwick) Water Treatment Works Upgrade

As part of our ongoing investment programme and to ensure the highest level of customer service, we are planning to extend and improve the existing Water Treatment Works at Murton, near Berwick. It is intended that the new works will be located adjacent to the existing buildings. The main construction work commenced in late 2018 and is due to complete in September 2020.

Project updates

Update by Joan Tatters

Good Afternoon,

As promised............

Please Login in order to comment on this update.

Update by Joan Tatters

Good Afternoon All,

So by now you will have noticed us!!!! We are currently setting up the site which needs to be prepared and established to suit the project and we will need to extend into the car park because of the area required.

There will be a reasonable amount of activity this week so please be a little more vigilant as we will be in and out of the site.  Mark, Steve and the team have been busy, stripping back the topsoil, laying aggregate, establishing the laydown area for materials and just making the area safe for work......so there is a lot of activity on the west side of the site.

Fingers crossed the team are expect to move into their temporary cabins within the site later today.

I will post some photos so you can see what's going on.

Don't forget if you have any questions just either write me a blog or use the "contact us" button on the project page or, you can always simply ask one of the site team.

 

 

Please Login in order to comment on this update.

Update by Joan Tatters

Good Afternoon Everyone,

Happy New Year!

Just thought I would send you the details of the road closure and the diversion we will be introducing from Monday 7th Jan. The new traffic arrangement will continue for approximately one month after which we will review the situation. Whilst we intend to have the closure on 24/7 we will review the the closure daily to try to minimise any impact. All I ask of you is to be that little more vigilant during our presence as there will be more vehicle activity.

Here are the site plans for the closure and diversion, if you want further information please drop me a line on the portal or use the "contact us" button on the project page

Road Closure PDF

Diversion PDF

Please Login in order to comment on this update.

Update by Joan Tatters

Good Afternoon,

Following on from Chris' update, I thought I would take this opportunity to introduce you to our Mott MacDonald Bentley team.

I am Joan Tatters, Customer Liaison Officer and I will take care of all customer enquiries during the project and you will notice I will be blogging a lot so please feel free to contact me either via the portal or the "Contact Us", I will out and about as well so please come along and say Hello if you see.

John Goose is our Contract Manager who will managing the project

Mark Smith is our Site Manager who will manage the day to day operations who will be assisted by

Stephen Rudkin the Works Manager.

John, Mark and Stephen have multipul years of experience in the construction industry and we all have worked on various projects with Northumbrian Water during this framework.

Wishing you all good health and happiness for 2019.

Here we are so you can put the names to faces should you see us:

 

Please Login in order to comment on this update.

Update by Chris Austin

Hi everyone

I'm Chris Austin the Project Manager for the Murton Water  Treatment Works (WTW)  Upgrade.

As part of our ongoing investment programme and to ensure the highest level of customer service, we are planning to extend and improve the existing WTW at Murton, near Berwick Upon Tweed.

The extension of the existing WTW facility will comprise of a new building, new settlement tanks, new disinfection tanks, modification to the site vehicular access and new areas of roads / hardstanding within the site.

We are shortly planning to commence with our construction activity at the site.    Initial preparatory works will start on site on Wednesday 14 November 2018 before the main construction works commence.

We're working in partnership with our framework partners Mott MacDonald Bentley to complete the construction work at the site which will take up to 12 months to complete with planned completion in December 2019.

We will share further information with you about this project and will also provide regular updates on progress and traffic management whilst works are in progress.

If you have any queries,  or want to make us aware of any additional assistance you require from us during this work, then please use the ‘Contact us’ button at the top of this page.

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers