Update by Brian Hall
Hi
Construction activities are now at the peak on the 3 sites and the teams are doing a fantastic job !
At Ramshaw and Butterknowle we are busy completing the new storm tanks and electrical building foundations. Duct work at Cockfield is nearly complete to allow the electrical experts to follow on.
Enjoy the bank holiday weekend. Hope it stays dry !!
Thanks
Martin