Update by Brian Hall
HI everyone
We are 80% way through the civil engineering part of the build. Cockfield is almost ready to accept the new inlet works. Chemical dosing installation has commenced at Ramshaw and is all going well. At Butterknowle we have been busy getting the foundation ready for the electric kiosk. Please take care when driving near the sites as we still have on going delivery's. Enjoy the weekend.
Martin