Good afternoon,
We hope you all had a lovely Easter Weekend!
I have included a plan here for you to view which shows the areas I am referring to below.
Pittington
Starting our update with the Gravity Drainage in fields 9 and 10, we have now constructed the discharge chamber, manhole chambers 1-7 along with the pipelines connecting the chambers together. The team are due to complete the enabling works including installing the sheet piles and frames ready for work being carried out to Manhole 8. To carry out excavation works to this chamber safely, a stone pad access platform has been built (see photos). Construction work to Manhole 12 has been carried out, ready for the 225mm pipeline to be tied into the existing manhole once coring works are complete. The pipework from Manhole 12 to the flow control chamber is also currently underway.
In field 11, we have excavated and shored Manhole 10 and Manhole 11 prior to carrying out the drill shot of the 250mm PE pipe between the two chambers. You may have already noticed that we have added traffic lights to Mill Lane while we carry out the drilling work from Manhole 10 to Manhole 8 which will run underneath the road. It is necessary for us to use trail holes to locate the gas main and water main so we can carry out the drilling work safely. We anticipate the traffic lights being in this area for up to three weeks. We do apologise for any inconvenience caused at this time.
Finally, in Pittington STW the new storm tanks are standing at their final height, and the kerbs, paving area and retaining wall are being constructed. We are also proceeding with the prep works for the MCC Kiosk base.
Sherburn
As mentioned in our last update, all the 5m shaft segments have now been installed in the backwash tank and the surround has been poured. The team are now ready to start constructing the top slab next week.
The NSAF legato block retaining wall is now in place.
Finally, the installation of the ducts adjacent to the proposed MCC Kiosk is almost complete.
Please feel free to leave a comment below if you have any questions, and a member of the project team will get back to you.
Speak soon!
Gaby
Please Login in order to comment on this update.