Good Afternoon,
As mentioned previously we were preparing for the installation of the sheet piles to the excavation which have now been installed. There will be ongoing works which will be to reduce the ground level within the sheet piled excavation, this will generate approx 1000t of excavation arisings that will have to be removed from site.
Once the excavation is complete we will be moving onto the reinforced concrete structure that will house the new tertiary treatment plant.
If you have any queries at all regarding our work in your area, please do not hesitate to contact us.
Thank you