Update by Rachel Rutter
Good afternoon all,
Today the crew have removed the site cabins and have started to downsize the site and grouted the backwash pipe.
Shutters are now in place for final slab pour next week.
Ongoing work continues which includes:
- Breaking out slabs for bollard installation
- Removing excess materials and waste from site
- Grouting Baseplates
- Drain and clean sump channel
- Change the motor to SF6/30 Mecana filter which is planned for Tuesday 6 September 2022
Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.
Thank you, hope you all have a great weekend!
Rachel