Update by Rachel Rutter
Good morning,
The crew have now completed the first section of drainage on Moor Crescent with a temporary reinstatement. Later in the project a permanent tarmac will be installed. This week the team continue with drainage works and 1050mm pipework is being installed.
On Friday 2 August 2024 the road closure on Moor Crescent was repositioned for a period of 3 weeks. Parking is restricted and we ask, if you require the use of your vehicle it is parked outside of the closure.
Thank you for your time!
Rachel
Please Login in order to comment on this update.