GENERAL PROJECT

Storm Overflows Environmental Improvements

To improve the resilience and enhance the performance of the sewer network in Northumbrian Water is investing in the overflows in West Rainton, Ludworth, Bishop Auckland and Skelton. This work will ensure we deliver sewerage services that meet the needs of current and future generations whilst improving the quality of our rivers and watercourses for the benefit of people, the environment and wildlife.

Project updates

Update by Rachel Rutter

Good afternoon,

I thought now is the perfect time to update you on the 5 projects and how the teams are progressing.

Moor Crescent/Barnard Avenue, Ludworth

The team have been working on 1050 tank and although they have faced some challenges due to weather and uncharted services this is due to be completed by Friday 8 November. The sewer separation on Moor Crescent and Barnard Avenue is being worked on over the coming weeks.

Pithouse Lane, West Rainton

The work to install new manholes in the highway is now complete and the traffic management will be removed from 15:00pm today. Next week the team will begin work on preparing the new CSO, ready for installation over the coming weeks.

Stanghow Road, Lingdale

Over the last couple of weeks, the team have set up the main compound area ready for work to begin. They have also created a stone road on Stanghow Road to allow entrance into the working area. Next week the team will be working on surveying manholes and drainage. If you see them in the area why not say hello!

Etherley Dene, Bishop Auckland

Although the team are working hard in the background, you won’t see them working in the road for the next few weeks due to urgent third-party work in the area. We understand how busy the roads can be this time of year and didn’t think it practical to have two companies working so close together at once. As always, the team and I will keep you updated when our work progresses.  

Finchale View, West Rainton

Work on Finchale View will begin WC 04 November, over the next week the team will be setting up the compound area and bringing in the required materials for work to begin.

Thank you for your time, have a great weekend!

Rachel and Alice

Please Login in order to comment on this update.

Update by Alice Blackett

Good afternoon

As three out of the 5 sites have now begun, we would like to take a moment to update you of the team's progress.

Pithouse Lane, Leamside 

All access works are now complete including haul road, compound and protection slab.

Traffic management is currently in place using 2-way traffic lights on Pithouse Lane whilst we complete Highways Drainage Works. Traffic management will be in place until Friday 1st November 2024.

Moor Crescent, Ludworth

The team have been working against the weather these last couple of weeks in order to progress with work. They have now completed work on two manholes and have lay the pipe work in between. Over the coming weeks the team will be working on the storm drainage and making sure that it is installed. 

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Thank you 

Alice and Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Etherley Lane Environmental Improvement Project

Morning all, 

This week i have had the pleassure to speak to many of the residents in the area to discuss the upcoming environmental improvement project in the Etherley Lane vicinity.

This work will help protect the environment and ensure that our sewer network continues to serve the community effectively.

I can confirm that the improvement work is planned to commence on Monday 14th October 2024.

Esh/Stantec will undertake this construction work which will comprise:

  • Surface water separation within Barrington Meadows.
  • 200m of new 225mm surface water sewer within Etherley Lane.

The creation of additional surface water sewer and combined sewer capacity will reduce the impact of rainfall on the sewer network protecting the environment through the resulting reduction in Storm Overflow operation.

The schematic which shows the proposal and working areas has been uploaded. We anticipate that our work will take up to 5 Months and a phased approach will be adopted with completion anticipated in April 2025 however, as with all civil engineering construction projects, unexpected delays can sometimes occur. I would like to thank you in advance for your cooperation while we complete this essential work.

Thank you 

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning

This week the team will be installing the new hydro brake into the existing manhole on Moor Crescent. Unfortunately the heavy rain has caused a change in the plans, but the team are working hard to be back on track. The temporary diversion will be installed to enable the construction of a new manhole and to allow the completion of the remainder of pipeline.

In the up coming coming weeks the team will be working on the installation of the storm drainage.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Thank you for your time

Rachel

Please Login in order to comment on this update.

Update by Alice Blackett

Good Morning

I hope you are all well.

Please see photographs for an update on how we are progressing at Pithouse Lane, Leamside.

The compund is now fully complete and protection slab has now been installed.

Installation of new drainage and haul road are yet to be completed.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning

As you may have seen on Thursday 5 September 2024 the road closure on Moor Crescent was repositioned to the junction close to the field entrance. Due to the location of the work vehicles are not able to follow the road around on Moor Crescent and we expect this section of work to be completed by 20 September 2024.

Parking will be restricted while work is caried out and we thank you for your patience and understanding while we complete these works. 

The team have continued to install pipe work this week as well as preparing the chamber and connections for further works.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Have a lovely weekend! 

Rachel

 

Please Login in order to comment on this update.

Update by Alice Blackett

Good Morning

I hope you are all well.

The site team are making good progress on the works at Pithouse Lane, Leamside.

The compound installation is 90% completed with the strip foundations of the protection slab going in today.

The protection slab itself is to be installed next week. 

Have a good weekend!

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

Esh have been making every effort to have the work outside the school completed prior to the school returning, in order to minimise distruption. We anticipate the upstream manhole will be build by Tuesday 3 September, with the traffic management in front of the school cleared for Wednesday 4 September.

A temporary reinstatement on the road is in place and a permanent reinstatement will be completed later in the year. 

Pipe installation will begin towards the end of road, close to the compound on Wednesday 4 September. Once the sewer installation is complete on Moor Crescent, the team will be moving onto Barnard Avenue to undertake further surface water separation work.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Have a lovely weekend! 

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

The team are progressing well at Moor Crescent and have installed 48 metres of the 1050-millimetre pipework, temporary reinstatements are being completed as the sections of road closure are complete.

Between today and Friday 30 August the team are aiming to complete the pipework installation outside of Ludworth Primary School.

Following on from this the crew will be constructing the manhole at the head of the line and finalising temporary reinstatements, with a thorough clean ready for the school returning Wednesday 4th September.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Thank you 

Rachel

Please Login in order to comment on this update.

Update by Alice Blackett

Good Afternoon

Following my visit to  the residents of Pithouse Lane last week, works began on the Storm Overflows Environmental Improvements Scheme yesterday 19 August 2024.

The team are currently undertaking some ground investigation works and have been digging trial pits to locate the water main. Please see photograph for reference.

Over the next couple of weeks, the team will be setting up site, stripping the topsoil, installing stone, welfare installation and installing a protection slab for the water main.

Please keep an eye out on our portal for future updates as the works progress over the upcoming months.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Thank you

Alice 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers