Update by Rachel Rutter
Good afternoon,
The team are progressing well at Moor Crescent and have installed 48 metres of the 1050-millimetre pipework, temporary reinstatements are being completed as the sections of road closure are complete.
Between today and Friday 30 August the team are aiming to complete the pipework installation outside of Ludworth Primary School.
Following on from this the crew will be constructing the manhole at the head of the line and finalising temporary reinstatements, with a thorough clean ready for the school returning Wednesday 4th September.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com
Thank you
Rachel