Update by Alice Blackett
Good afternoon
As three out of the 5 sites have now begun, we would like to take a moment to update you of the team's progress.
Pithouse Lane, Leamside
All access works are now complete including haul road, compound and protection slab.
Traffic management is currently in place using 2-way traffic lights on Pithouse Lane whilst we complete Highways Drainage Works. Traffic management will be in place until Friday 1st November 2024.
Moor Crescent, Ludworth
The team have been working against the weather these last couple of weeks in order to progress with work. They have now completed work on two manholes and have lay the pipe work in between. Over the coming weeks the team will be working on the storm drainage and making sure that it is installed.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Thank you
Alice and Rachel