![](/Themes/NWL/images/avatars/avatar-00.png?autorotate=true&width=40&height=40&mode=crop)
Update by Graeme Ridley
Good afternoon,
Project update with regards the ongoing construction of Northumbrian Water's new 'screenings facility' building, which is adjacent to our existing sewage pumping station.
The work that remains is all contained within the area behind the temporary fencing, directly west of Sheehan Court.
Due to delays in construction of the 'new screenings' facility building, the completion date is now forecast for September 2024. This has been due to severe weather conditions and more time required for the construction of the foundations to the building.
In response to the severe weather conditions on 9th April 2024, our flooding teams have been in direct contact with Customers effected and are working closely with them to provide support.
Graeme Ridley.
(Project Manager)
Please Login in order to comment on this update.