Update by Anthony Birkett
Hi Everyone
I've been Wapping Burn today and met with Darren, so we'd like to provide an update about progress. As you can see, things are within touching distance of finishing. The compound is being gradually removed and will be off site by the end of next week.
On Wednesday 20 December 2017 we have booked a contractor to permanently reinstate the roads in the entrance to the access to Icarus and in Hunter Road in the junction with Swan Road. This will leave a small amount of reinstatements to be completed in January. The work on Wednesday will be managed by three way traffic lights but we don't expect significant impact on traffc, the Traffic Management contractor will be on site and will manage any traffic build up if there is any.
Hope you all have a great Christmas
Tony
Please Login in order to comment on this update.