Update by Christopher Bond
Good Afternoon
Firstly, to introduce myself, my name is Chris Bond and im a Project Manager at Northumbrian Water and I want to let you know details of essential work we’ll be carrying out in your area. Along with the rest of the project team, we will be keeping you updated as the project progresses.
You will have recently received a letter explaining about the essential refurbishment works to our underground Sewerage Pumping Station (SPS) at Warkworth Stanners, which will protect the environment and help ensure that the site always remains fully operational.
Together with our supply partner, RetroFlo we propose to carry out £600k of investment. The works will involve repair and refurbishment work to the SPS and conversion work to create a wet well.
Works will start in Autumn 2024 and we anticipate this will take up to 4 Months to complete.
If you have any queries or comments or would like to speak to someone from the project team please get in touch using the ‘Contact us’ button at the top of the page. We’d really like to hear from you.