Update by Anthony Birkett
Hi Everyone
Sorry we've not been in touch for a while. All works are now complete across the site. However, we will need to return later this month to install some hedges to the field opposite Lynemouth Way and a section adjacent to the A1, accessing from Maynard Street. This is because they need to be planted at a certain time of the year to ensure optimum growth.
Next year, we will return to complete the rotavating and seeding on Lynemouth Way and Maynard Street.
The compound will remain in place and will be used for another nearby scheme until March 2018.
We would like to take this opportunity to thank you all for your patience and understanding while we completed these works.
Regards
Tony