Morning all,
It's been a while since I posted anything on here (I've been on holiday in Spain!!) so I thought I'd make it my priority task this morining.
A lot of progress has been made since last writing and I'm pleased to say we are currently on programme, despite a lot of challenges presenting themselves as the works have progressed. We've had more pipe collapses resulting in emergency works being carried out in the farm fields as well as poor weather and existing flows to overcome. Lets go through an update from the bottom of the site to the top....
Our lining operations to the Southern end of the project (East of the A1 and access via Featherstone Grove) are now complete. The haul road we had installed has been removed along with all of our equipment and pipe work. A landscaper will attend site this week to begin rotavating and seeding the topsoil. On the opposite side of the A1, similarly linining operations are complete and the haul road removed. There is a little more reinstatement work required to this area; replacing footpath kerbs, laying new tarmac as well as soft landscaping. These operations will hopefully be complete and our fencing removed in the next couple of weeks. A great milestone having complete the lining operations, all thanks to the dedicated team involved including our own directly employed operatives as well as our subcontractor, JetAire and specialist pump hire company, Exsel Pumps.
Further North on the project our drainage operations are nearing the final stages. We have been moving back along our newly laid pipe, making all the fiddly connections in order to transfer flows. I mentioned earlier the many challenges we have been faced whilst making these connections but our subcontractor, MJR Groundworks, have done a great job putting a lot of hard work in to get where we are today!
What to expect in the next couple of weeks...
Other than the soft landscaping mentioned above, we will be removing our temporary compound set up at Roseden Way, replacing kerbs and laying new tarmac to the footpath. Lynemouth Way compound will be removed, including the haul road to the work area and the footpaths and surround field reinstated. Our works will then focus on the final online pipe connection outside our main compound off Brunton Lane. Grouting operations are due to commence this week which will see plant and equipment mobilised for a day or two at Roseden Way. The grout will be used to fill sections of the redundant pipe that pass beneath the road and future development.
More from me later in the week hopefully with more good news and progress photos!
Mark
Please Login in order to comment on this update.