Update by Rachel Rutter
Good afternoon,
The team are progressing on schedule with tarmac reinstatement work to trenches and footpaths taking place on Thursday 29 August within Conyers School.
Within Yarm School grounds the team are setting covers and frames to manholes, removing the stone haul road, completing topsoil reinstatement and removal of fencing.
All plant and materials will be removed from both areas by Friday 30 August ready for the school year to begin.
Traffic management will be in place on A67 from Friday 30 August using 2-way lights to allow the road to be resurfaced, we expect the work to be completed within 1 day.
The carlow tank is excavated and ready for work to start on Monday 9 September, with the rising main installation ongoing.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Thank you
Rachel