GENERAL PROJECT

WINEP - Kirklevington Transfer

AS PART OF A £5 MILLION SCHEME, WE WILL BE CARRYING OUT ESSENTIAL WORK TO IMPROVE THE PERFORMANCE AND FLEXIBILITY OF OUR WASTEWATER NETWORK AND WASTEWATER TREATMENT WORKS IN THE KIRKLEVINGTON AREA. THE SCHEME WILL HELP TO IMPROVE THE WATER QUALITY OF THE THESE AREAS FOR THE BENEFIT OF PEOPLE, THE ENVIRONMENT AND WILDLIFE AND ENSURE THAT CRITICAL WASTEWATER ASSETS CONTINUE TO SERVE THE COMMUNITY EFFECTIVELY.

Project updates

Update by Rachel Rutter

Good morning all,

We wanted to take this opportunity to wish all our customers a Merry Christmas and all the very best for 2025.  We would also like to thank you all for your patience and understanding whilst we have carried out our works.

The site teams are taking time off to be with their loved ones over the Christmas and New Year period and will be finishing on Friday 20 December 2024 to return to work on Monday 6 January 2025. 

If you have any concerns over the Christmas and New Year period, please contact us by emailing nwl.customer@esh.uk.com.

Merry Christmas to you all, stay safe and wrap up warm!

Thank you 

Rachel, Alice and Christine.

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning 

The roof slabs on the Carlow Tank were lifted on Monday 4 November, with the pour completed on Friday 8 November.

Ducts have been installed and the team have begun digging the kiosk base. Temporary work will be removed in the coming weeks.

All work is now taking place within the sewerage treatment works. 

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Thank you for your time.

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning 

As mentioned in previous updates the team are working mainly on site associated with the Carlow tank and drainage within the Sewerage Treatment Works.

The benching has been completed to the Carlow tank, with roof slabs to be lifted on Monday 4th and 5th November.

Slab preparation is underway then the team will pour the roof slab on Friday 8th November and the Carlow to be demobilise after completed.

Drainage work is ongoing within existing Sewerage Treatment Works, with the team excavating by hand.

Installation of the ducts and chambers to supply power/comms to new tank and rising mains are underway.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Thank you for your time, have a great weekend!

Rachel

 

 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

Can you believe this weather!

The team have been battling the elements and are working on the Carlow tank next to the existing Sewerage Treatment Works, with construction underway from Monday 30th September. All wall infills and main base have been poured and they are getting ready to form the benching over the coming weeks.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Thank you for your time

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning,

The rising main has been installed from Conyers school to the Carlow tank on site, this has been air tested and passed.

Topsoil reinstates are underway throughout the project, once areas have been completed.

Carlow tank construction is ongoing, with walls and base pour to be started from Monday 30th September.

New drainage installation is ongoing within Kirklevington Sewerage Treatment Works.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Thank you for your time

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon, 

Following on from my last update the team began work on the Carlow tank Monday 9 September 2024.

The team are now installing precast sections and units, within the tank. This work will continue into the next week.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Have a great weekend!

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

As you may have seen the team have been working throughout the school holidays to make sure the work required within Conyers and Yarm School was complete ready for the new term time.

Within Conyers School all drainage has been installed and signed off, including CCTV works and air testing completed. Tarmacking is complete and all areas cleaned and tidied. Herras fencing remains in place to protect the new grass seeded area

Yarm School playing field has been reinstated, with the car park all cleared and all fencing removed from site. A small section of work is left to carry out such as concrete surrounds to manhole lids and air testing to the pipework.

The rising mains are installed all the way to the Carlow tank, which has been excavated and ready for Carlow to start on Monday 9 September.

The remaining air valves and wash out chambers are being constructed, with topsoil reinstatement to be completed.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Thank you, have a great weekend!

Rachel

 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

The team are progressing on schedule with tarmac reinstatement work to trenches and footpaths taking place on Thursday 29 August within Conyers School.

Within Yarm School grounds the team are setting covers and frames to manholes, removing the stone haul road, completing topsoil reinstatement and removal of fencing.

All plant and materials will be removed from both areas by Friday 30 August ready for the school year to begin.

Traffic management will be in place on A67 from Friday 30 August using 2-way lights to allow the road to be resurfaced, we expect the work to be completed within 1 day.

The carlow tank is excavated and ready for work to start on Monday 9 September, with the rising main installation ongoing.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Thank you

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning

The traffic management on Thirsk Road/A67 will be removed on Wednesday 14 August.

The team are continuing work within the school grounds as well as beginning the excavation for the installation of the carlow tank (concrete storage tank).

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Thank you

Rachel

Please Login in order to comment on this update.

Update by Rachel Rutter

Hi Everyone, 

The site fencing and topsoil strip is now complete throughout the main site working areas. Archaeology holes are all completed, and nothing reported.

Investigation works are ongoing within Yarm Sewerage Treatment Works and Northumbrian Water have issued structural surveys, including vibration monitoring.

You may have seen our team have begun work on Yarm School playing fields on Green Lane, installing fencing and completing a topsoil strip.

Traffic management is in place on Thirsk Road using 2-way lights, which will repositioned throughout our work. We will keep you updated as work progresses.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com.

Thank you for your time.

Rachel

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers