Update by Rachel Rutter
Good morning,
Hope everyone had a lovely weekend!
We wanted to take this opportunity to introduce ourselves to you all, we work for the contract partner, ESH Stantec who will be delivering the work in this area. You may have seen our crews in the area starting the preparation work, please feel free to approach the crews and ask any questions. Christine, Alice and I will also be out and about alongside Northumbrian Waters Project Manager David Greensmith speaking to customers whilst these works take place.
As mentioned, the team have begun preparation work, which has included stripping topsoil, preparing the compound and installing site roads. This week you may see fencing being erected in the playing fields on Green Lane to allow archaeology trial holes to be completed.
We will endeavour to update this portal with information as we move around the area.
Thank you, have a great week!
Rachel, Christine & Alice