Update by Rachel Rutter
Good afternoon,
As you may have seen the team have been working throughout the school holidays to make sure the work required within Conyers and Yarm School was complete ready for the new term time.
Within Conyers School all drainage has been installed and signed off, including CCTV works and air testing completed. Tarmacking is complete and all areas cleaned and tidied. Herras fencing remains in place to protect the new grass seeded area
Yarm School playing field has been reinstated, with the car park all cleared and all fencing removed from site. A small section of work is left to carry out such as concrete surrounds to manhole lids and air testing to the pipework.
The rising mains are installed all the way to the Carlow tank, which has been excavated and ready for Carlow to start on Monday 9 September.
The remaining air valves and wash out chambers are being constructed, with topsoil reinstatement to be completed.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com
Thank you, have a great weekend!
Rachel