Good morning,
The rising main has been installed from Conyers school to the Carlow tank on site, this has been air tested and passed.
Topsoil reinstates are underway throughout the project, once areas have been completed.
Carlow tank construction is ongoing, with walls and base pour to be started from Monday 30th September.
New drainage installation is ongoing within Kirklevington Sewerage Treatment Works.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com
Thank you for your time
Rachel