AS PART OF A £5 MILLION SCHEME, WE WILL BE CARRYING OUT ESSENTIAL WORK TO IMPROVE THE PERFORMANCE AND FLEXIBILITY OF OUR WASTEWATER NETWORK AND WASTEWATER TREATMENT WORKS IN THE KIRKLEVINGTON AREA. THE SCHEME WILL HELP TO IMPROVE THE WATER QUALITY OF THE THESE AREAS FOR THE BENEFIT OF PEOPLE, THE ENVIRONMENT AND WILDLIFE AND ENSURE THAT CRITICAL WASTEWATER ASSETS CONTINUE TO SERVE THE COMMUNITY EFFECTIVELY.

Update by Rachel Rutter

Good morning 

The roof slabs on the Carlow Tank were lifted on Monday 4 November, with the pour completed on Friday 8 November.

Ducts have been installed and the team have begun digging the kiosk base. Temporary work will be removed in the coming weeks.

All work is now taking place within the sewerage treatment works. 

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Thank you for your time.

Rachel

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers