Update by Rachel Rutter
Hello all,
Hope you are all well!
The team have now installed the valve chamber and flow meter chamber, as well as the precast units installed by Carlow concrete and lifted into position by Mammoet cranes.
Core drilling to units, installation of ducts and mechanical pipework including pumps will be actioned within the coming weeks. Commencement of the installation of remaining drainage lines will also follow.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Thank you, Rachel