Update by Rachel Rutter
Good morning
Hope you are all well!
As you might have noticed, we are now back on site, with works continuing on the Rising Main. The last two remaining directional drilling works have been completed along with the associated Rising Main Pipework. All the Rising main Pipework across the scheme is now installed with the exception of the wash out chambers and pressure testing the system which is scheduled to commence this week.
The crew have installed the overflow chamber with the extraction/removal of all the drive pit shoring. The 300-diameter overflow pipework to the existing overflow pipeline is ongoing in readiness to construct new online manhole.
All the drainage and manholes have been installed up to proposed new discharge chamber with the exception of approx 15 meters of pipework. Topsoil reinstatements are being carried out.
The new MCC Kiosk base has been completed with our contractor Retroflo on site to install the Kiosk, with the MCC to follow at a later date. Installation of the new wet well scaffolding is in preparation.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Thank you have a lovely weekend!
Rachel
Please Login in order to comment on this update.