Update by Rachel Rutter
Good morning,
Following on from the previous update the earthworks and stoning up operations have continued, and the team have excavated and installed the temporary stone access road down to the proposed working easement. The team have also installed the temporary timber bog mats as protection to the HP gas main at the entrance to Longnewton.
The existing access track has been excavated and widened to form a public walkway, followed by installation and construction of our stone temporary site compound set up.
Heras fencing and posts along with weld mesh gates has been installed for security. Asbestos pre-demolition surveys to Longnewton & Goosebeck have been completed including BSG Ecology attended site on Wednesday 5 June to carry out a Bat climb to the tree alignment.