Update by Rachel Rutter
Good morning,
Following on from my previous update, the team have begun with the easement fencing works with the installation of post and wire. Temporary highway site entrance posts and signage has been installed.
The team continue to work with BSG Ecology to carry out hedgerow and woodland inspections for nesting birds.
Archaeological trial trenches are ongoing and will continue throughout the scheme, priority trenches will be side by side to collate information.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Thank you for your time!
Rachel