Good afternoon,
As of Friday 29 November 2024, Archaeology will finish within the current area and will be returning for a watching brief WC 9 December 2024.
Work has been completed on The Front, with the team continuing work within the Sewerage Treatment Works.
Auger boring has commenced at Goosebeck and will be completed within 1 week, we dont expect this to cause too much disruption.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.
Thank you for your time!
Rachel