Good Morning Everyone,
Here are some photos of this weeks progress, the roof is starting to take shape on the Treatment Building and the brickwork is progressing nicely.
The team have poured a 2nd round of concrete into the Waste Water pumping station.
The final leg is about there along the B6525 and we should be finished by Tuesday next week. All the tarmacing has been complete in the industrial estate which is just to pressure test.
Stay safe.